What a Home Construction or Remodeling Agreement Should Make Clear

A plain-language checklist of scope, price, schedule, payment, change, risk, warranty, and closeout questions to resolve before work begins.

Homeowners and a construction professional reviewing organized project drawings and agreement documents.

A construction agreement should turn expectations into an operating system for the project. It cannot predict every condition, but it should explain what will be built, what is not included, how decisions are made, when money moves, and what happens when facts change.

HHM develops the project agreement around the transaction, responsible parties, property address, scope, pricing method, payment path, applicable requirements, and customer rights. Qualified North or South Carolina counsel addresses transaction-specific lien, cancellation, licensing, enforcement, and dispute terms when needed.

Correct parties and property

Confirm the legal customer, legal contracting entity, property address, notice addresses, and signer authority. Verify applicable credentials and insurance independently. A trade name, salesperson, or website may not be the party responsible under the agreement.

Scope and documents

List incorporated drawings, specifications, proposal versions, selections, allowances, addenda, and exclusions. Establish which document controls if they conflict. Identify owner-supplied items and who handles ordering, delivery, damage, storage, installation compatibility, and warranty.

Price and allowances

State whether pricing is fixed, cost-plus, unit-priced, time-and-materials, or another structure. Define taxes, permit fees, freight, contractor markup, allowances, alternates, contingency, and reimbursable expenses. For each allowance, identify quantity, assumed product level, labor treatment, and reconciliation.

Payment milestones

The agreement should explain how payments relate to contractual milestones or documented progress. Address deposits, retainage if used and permitted, invoices, payment method, draw inspections, late payment, disputed amounts, lien documentation, and final payment conditions. The agreement, lender requirements, and applicable law control these terms.

Schedule and delays

Identify expected start/completion framework, prerequisites, owner decisions, material lead times, permitted delay causes, notice requirements, schedule updates, and the effect of changes. Avoid treating a target date as an unconditional guarantee when permits, inspections, weather, utilities, or concealed conditions remain unresolved.

Changes and concealed conditions

Define who can authorize changes, required documentation, pricing method, schedule effect, emergency authority, and treatment of unknown site or building conditions. Set approval limits for exploratory or time-and-material work.

Permits, design, and trade responsibility

State who provides design and engineering, obtains permits, schedules inspections, coordinates utilities, and performs regulated trade work. Identify the authority having jurisdiction and any HOA, historic, environmental, or lender requirements that remain separate.

Protection, access, and living conditions

Address work hours, property access, keys/codes, pets, occupied-area protection, utilities, temporary facilities, dust/noise, hazardous materials, owner belongings, parking, security, cleanup, and photography/privacy. Operational site documentation and optional marketing permission should be separate.

Insurance, damage, and risk

Identify required insurance, responsibility for existing conditions, stored materials, theft, weather, property damage, and owner occupancy. Ask an insurance professional about builder’s risk or renovation coverage appropriate to the project.

Completion and warranty

Define substantial completion if applicable, punch process, final inspection, occupancy approvals, manuals, registrations, keys, lien documents, final payment, and warranty start. Separate manufacturer product coverage from contractor workmanship and excluded maintenance, abuse, movement, moisture, or third-party work.

Suspension, termination, and disputes

Review notice, cure, suspension, termination, payment, material ownership, demobilization, dispute-resolution, governing-law, and attorney-fee terms with qualified counsel as appropriate. Determine whether any cancellation right applies to the particular transaction before signing or paying; do not assume every construction agreement has the same right.

Next step: Create a one-page responsibility matrix from the agreement. If the team cannot tell who owns a task, when it is due, and how completion is proven, clarify it before construction.

Turn the range into a real scope

Send your project details to HHM

Use the planning range to choose the closest budget range in the existing HHM project form. HHM must review the property, scope, selections, delivery, and trade requirements before providing any proposal.

Use the HHM form for project details and scheduling. Please keep highly sensitive information out of this first request. Privacy · Terms

How HHM organizes the project

The project address and requested work let HHM organize the responsible permitting path, required trades, site review, products, scheduling, and project team for the exact scope.

Open the HHM project-request form in a new page

Plan My HHM Project

Choose a site visit or Google Meet. HHM carries the saved project purpose and address into scheduling.

If the form is unavailable, email group@hhmcustomhome.com with a non-sensitive summary and your preferred response method.